JSE Provided Mechanical, Electrical, and Plumbing Design Services for this $33,500,000 Project
The Town of Marion, Village of Palmyra, and Town of Macedon executed a municipal cost sharing agreement to consolidate the wastewater from the three municipalities into a single regional WWTP. Jade Stone Engineering joined the team to provide mechanical (HVAC), electrical, and plumbing engineering, bidding, and construction phase services.
Design scope items include:
New electrical service and associated gear at 3 locations
New emergency generator systems at each location (parallel 750kW units, 300 kW unit, 200kW unit)
New switchboard
New distribution gear
Design of NFPA 820 compliant systems
Design of lighting layouts with high efficiency LED lighting
This project includes, but is not limited to, the construction of a new WWTP in the Village of Palmyra, decommissioning of existing Town of Marion and Town of Macedon WWTP and construction of new pumping stations at each location.